LSST + GMT + MMT + Magellan, strategic planning. 

CWS May 25 2014

LSST commissioning is scheduled for 2019, operations in 2020. 

four-mirror version of GMT is also planned for 2020 first light. 

MMT and Magellan are both presumed to remain in operation. 

The question is how the CfA can best use this combination of resource to address scientific questions of interest. 

SystemapertureFOVnotes
LSST6.510 sq degongoing photometric survey
MMT6.5? 
Magellan x 26.50.25 sq deg 
GMT Phase 18.5 *4? 