  • DeeDee sent mask designs to Joe.
  • Reached out to everyone with image quality team action items to get their status and updated the Image Quality team meeting notes page
  • Started putting an IQ ComCam plan together: https://confluence.lsstcorp.org/display/LSSTCOM/ComCam+Image+Quality+Commissioning+Plan
  • Got the threaded tube back from the machine shop. It seems to fit well. I really need the last piece (that was supposed to be made first...). Sent an email to them begging them to make the last piece.
  • Started making a list of tests to run and things to do for the CBP Calibration system: CBP Calibration System To Do
  • Talked to Parker about how to update the electrometer CSC to be able to handle both the Keysight and the Keithley CSC. Notes on the confluence page: https://confluence.lsstcorp.org/display/LTS/Electrometer+CSC+Notes
  • Talked to Sandrine about the Image Quality commissioning plan. I've updated the confluence page accordingly. 
    • One conclusion is that at the next IQ meeting we'll discuss whether to install DIMSUM or DSM in Simonyi (what would be needed for each to work, etc.)