Item | Detailed Description | Deadline |
---|---|---|
Conceptual Design Review | Meghan will create a detailed presentation (4-5 slides) describing the system we are to build and its purpose, and be as detailed as possible (including part numbers). Meghan will then present this slide deck to Prof. Stubbs and Elana - we will find a time hopefully before Friday Feb 2. | Friday, Jan 26 |
Software/Hardware Preliminary Decisions | Meghan and Prof. Stubbs will decide on:
Above hardware should then be ordered (asap). | Friday, Jan 26 |
Steerable Collimated Beam | Have a single, steerable collimated beam working. This will involve:
| |
Scale to Six Steerable Beams | Add the other beamsplitters so that the system is scaled to its full size.
| |
Local Telescope Test | Set up the system for the telescope we have here to test the differential monitoring.
| preferably before Friday, April 26 but there is some wiggle room |
Initial steps:
...
Beamsplitter options, CWS Jan 26 2024 |
vendor | part # | size | specs | price |
---|---|---|---|---|
Newport | 20BC17MB.1 | 50.8 x 50.8 | lambda/4 | $635, stock |
Edmund | #32-704 | 50.0 x 50.0 | lambda/4 | $539, stock |
Thor | BS031 | 50.8 x 50.8 | lambda/4 | $564, stock |
Initial steps:
- read control manual for whichever steerable mounts we order
- read some of the papers from the slack
- make wiki organization clearer - separate page for meeting notes
- read up on kinesis software
longer term: mac mini windows equivalent
smaller piezo setup