Project Summary
Harvard is participating as a development partner with Ex Libris to explore use of a Robotic Process Automation tool with the Alma/Primo (and beyond) integrations. If Ex Libris determines the tool will be moved to production, Harvard will determine if we should move forward with full adoption.
Project Timeline
Phase 1 (November-December 2024)
Ex Libris Partnership kickoff - November 21, 2024
LTS Onboarding of Tool - December 2024
Documenting Initial Use Cases - December 2024
Phase 2 (January-March 2025)
Implementation of Initial Use Cases - January - March 2025
Development of local documentation - January - February 2025
Prioritization of additional use cases - March 2025
Phase 3 (April -June 2025)
Implementation of addition use cases - April - June 2025
Pilot Project Retrospective - January - June 2025
Adoption Decision - June 2025
Additional Use Cases
coming soon!
Pilot Project Team
Laura Morse, LTS - Lead
Corinna Baksik, LTS
Julie Petzold, HL Access Services
Allison Powers, LTS
Amanda Schmidt, LTS
Colin Van Alstine, HL ITS
Elizabeth Vernon, Widener Judaica
Gerry Walden, HL ITS
Kara Young, LTS