I. Problem/Value Statement

Problem Statement

TBD

Business Value

TBD

...

TBD

...

The current DRS storage infrastructure (disk and tape) is in the final year of its service term and must be replaced. At the same time, DRS business owners would like to expand the range of storage options (e.g., cloud, external, etc.) and provide greater flexibility in replication policy.

Business Value

This storage refresh is critical for maintaining continuity of DRS service. It will also have the benefit of anticipated lowering of provisioning/operational costs, which then can be reflected in reduced DRS pricing. Support for an expansion of the range of storage options will streamline future incorporation of new technical solutions. It also enables implementation of policy-driven replication that provides better alignment of curatorially-designated value and goals with the technical characteristics of various storage components that best ensure those goals. This in turn will reduce overall costs (by minimizing the number and type of replicas) and maximize use of finite resources (space no longer used for a copy of A can now be used for a copy of B).

II. Vision and Approach

The provisioning of infrastructural capacity will place an emphasis on leveraging existing storage capabilities within the University (e.g., FAS RC) and consortial/commercial options outside the University (e.g., NESE, Iron Mountain). Conceptually, the DRS will now incorporate a storage broker architecture in which each file will be assigned a curatorially-designated storage classification that will control the variable degree of replication. New pricing will reflect the underlying provisioning/operating costs of the various storage options. Billing will reflect the differential prices of the various storage options utilized for a given file.

III. In Scope/Out of Scope

In Scope

Essential interface components

  • BatchBuilder
  • TBD
  • WebAdmin

Essential interoperability components

    TBD
  • Starfish storage management infrastructure

Essential infrastructure components

...

  • HUIT Research Computing managed storage infrastructure at Markley
  • FAS RC storage infrastructure at MGHPCC
  • AWS S3 Infrequent Access
  • Tape infrastructure at NESE
  • Tape warehousing at Iron Mountain
  • Snowball devices for movement of deliverable content to S3
  • Oracle DB
  • Fscheckd monitoring script
  • Quarterly billing script

Out of Scope

  • TBD

...

  • Interoperability with storage at FAS RC's HPC cluster at MGHPCC
  • Interoperability with USC DR

IV. Deliverables/Work Products

...

  • TBD

...

  1. HUIT Research Computing ECS at Markley
  2. FAS RC ECS at MGHPCC
  3. AWS S3 Infrequent Access
  4. Tape at NESE
  5. Tape at Iron Mountain
  6. Encryption of level 4 content into the tape environments
  7. Definition of OCFL structure for ECS file system and S3 object storage
  8. Retrospective classification of the storage class of all existing files
  9. Extension to DB schema
  10. BatchBuilder and WebAdmin support for storage (re)classification
  11. New pricing scheme based on partial cost recovery
  12. Revised quarterly billing script supporting non-uniform storage replication
  13. Updated BatchBuilder and WebAdmin online documentation and training material
  14. Switch to a different SFTP client and updates of depositor scripts to interact with ECS-hosted drop boxes; updates to "remote dropbox" setups that exist for Media Preservation, Imaging Services and Harvard Art Museums - related training, testing and documentation

Definition of "Done"

The DRS Refresh project will be considered done when:

  • TBD

...

  1. New hardware/software components are fully deployed
  2. Migration of all retrospective content to new storage environment
  3. Disposition of all prospective content to new storage environment
  4. BatchBuilder and WebAdmin updates are complete and training and documentation describe how to specify/update curatorial storage class attribute
  5. Dynamic storage reallocation (delete/copy as necessary) fully functional at point of initial deposit and on an ad hoc basis via WebAmin
  6. Fscheckd monitoring script re-written and pointed at all new storage options
  7. VPDR/LLT approval of new pricing scheme in consultation with stakeholders
  8. Quarterly billing script supports non-uniform storage replication
  9. Decommissioning and removal of old equipment

V. Stakeholders and Project Team

Stakeholders

Stakeholder

Title

Participation

TBD

TBD

TBD

TBD

Stephen Abrams

Head of digital preservation/ DRS business owner

Use cases, requirements, conceptual design

Stewardship Standing Committee


Review/comment

DRS collection managers


Review/comment/training

Harvard media and image digitization and preservation practitioners

  • Head of Media Preservation
  • Head of Imaging Services
  • Director of Digital Infrastructure and Emerging Technologies at Harvard Art Museums
  • Other media and image digitization and preservation practitioners who deposit and administer DRS content

Review/comment/test

Project Team**

Team Member

Role(s)

Affiliation

Stephen Abrams

Business owner

DPS

Tricia Patterson

Business owner

DPS

Vitaly Zakuta

Project manager/Scrum master/Analyst

LTS

Anthony Moulen

Architect

LTS

Andrew Woods

Consultant

LTS

Sharon Bayer

Infrastructure project manager

LTS

Chris Vicary

Technical lead / software engineer

LTS

David Neiman

Software engineer

LTS

Jessica Jassal

Software engineer

LTS

Valdeva Crema

Software engineer

LTS

Tom Scorpa

ProdOps lead / storage manager / systems administrator

LTS

Jason Knight

ProdOps / systems administrator

LTS

Benson Smith

DB admin

LTS

Julie Wetherill

Agile product owner / Analyst/ QA/ Documentation/training

LTS

Janet Taylor

UI/UX (4/27-on)

LTS

** Other team members may be added if work requires it

...

VI. Schedule

...

Phase

Phase Start

Phase End

Milestone

Milestone Date

Planning

3/9

3/29

Project Charter approved by all stakeholders


3/29

Preparation

3/30

4/12

Technical design complete

4/12

Development


4/13


8/16

All development tasks are complete


8/16

Move to Production

...


8/17


8/30

Move to production complete and accepted by stakeholders


8/30

VII. Key tasks and outcomes

Tasks

Outcomes

Responsible Parties

Approve Project Charter

Agree on Project Charter with regards to:

  • Stakeholders

  • Scope

  • Deliverables

  • Schedule

Business Sponsor

Meeting schedule

Sprint

ceremonies 

ceremonies

Project

Co-Managers

Manager

Project infrastructure

  • Populate Jira project board

  • Set up wiki page for LTS

Operations 
  • Operations

  • Set up dev/qa environments

  • Provision code repository

Project

Co-Managers and Business Owner

Operational Resources

Manager, Tech Lead, Architect, ProdOps

Development

  • Implementation of user stories

  • Based on scope and deliverables from charter

  • Reviewed and accepted by Product Owner

Project Team

Communication & Outreach planning

  • Demos to stakeholders

  • Email communication

  • Live updates to stakeholders (monthly?)

Project

Co-Managers

Manager; Business Owner

Move to production

Operational Resources and


Project Team

...

VIII. Assumptions, Risks, and Constraints

Constraints

...

  • Service contracts on existing hardware expire in September 2021
  • Updated software needs to be in production before start of Fall Semester 2021

Assumptions

    TBD
  • Prior completion of BatchBuilder Java upgrade

Risks

  • Risk: Work extends beyond the August 31 expiration of existing hardware
  • Plan:
  • Impact:
  • Owner:

...

...

Appendix

Definitions of Roles

  • Business Owner - Provide vision and direction of product
  • Product Owner - Define, prioritize, and accept work done for project
  • Project Manager - Maintain project schedule and communication
  • Scrum Master - Lead, guide, and assist project team through development work
  • Business Analyst - Provide insight into user needs to inform and refine work stories
  • Technical Lead -Lead technical design and development
  • Architect - Provide technical architecture for the solution
  • Software Engineer - Update and build software to accommodate new storage architecture
  • Production Operations - Administer new storage solution system and provide insight into its operation
  • DB Admin - Administer databases to accommodate needed functionality and facilitate needed changes
  • UI/UX - Create wireframes / mockups of new/updated UI components, and provide guidance on usability of new/updated functionality