Finalize GEN Inventory project: February 2022
- Collections analysis: February - April 2022
- Packing period and shift of materials off-site: March - May 15, 2022
- Movement of library staff into Phase 1 temporary work spaces: May 15, 2022 - May 30, 2022
- Locations requestable again: TBD May 23rd
- Renovation Construction Phase 1: May 31, 2022 - Jan 31, 2023
- Movement of library staff into Phase 2 work spaces: TBD
- Renovation Construction Phase 2: TBD
...