  • Finalize GEN Inventory project: February 2022

  • Collections analysis: February - April 2022
  • Packing period and shift of materials off-site: March - May 15, 2022
  • Movement of library staff into Phase 1 temporary work spaces: May 15, 2022 - May 30, 2022
  • Locations requestable again: TBD May 23rd
  • Renovation Construction Phase 1: May 31, 2022 - Jan 31, 2023
  • Movement of library staff into Phase 2 work spaces: TBD
  • Renovation Construction Phase 2: TBD

...