Section

Isometric Drawing, Still Image Representation



Objectives

  • Show spatial depth, project movement in space.
  • Show activity in the process of happening.
  • Show shadows, how light goes through the building.
  • Site relationship to the context, what is happening in the background, which other buildings are present, how it relates to the street.



Prerequisites

  • Set up Rhino layers
      • Set up ten different linework types
        • CUT  Heaviest lines. refers to structure and main wall being cut at about 4ft from finished ground level

        • SPATIAL  - Medium lines. linework geometry beyond the cut plane reflecting a spatial edge

        • SURFACE  - Light lines. (optional) division between co-planar geometries - for example joints on floor finishes

        • GLAZING  - Medium lines. cut line corresponding to transparent glazing

        • FURNITURE - Light lines. projected geometries of furniture below cut plane

        • PEOPLE - Light lines. projected geometries of occupants below cut plane

        • VEGETATION - Light lines. flora below cut plane

        • BELOW - Lightest lines. very light lines reflecting background context geometries beyond cut plane.

        • ABOVE - Light, dashed lines. dashed lines corresponding to significant geometries above

        • HATCH Variable lines depending on hatch type. layer to host hatch geometries

Prepare




1. Prepare the linework (

25min

0.5 Hour)

  • Cut the plan where you will draw the section and rotate
  • Add the cut line (longest line in diagram) then add the following lines
    • 1m below the line for the second linewidth (spatial)
    • 3m below that second line, add a third line for the third linewidth (surface), below that will be everything that remains in the lightest color, maybe furniture layer
    • About 3m above the cut line add two lines which generate the height of each floor, from floor below to floor above

Image RemovedImage Added


  • Once these are added, start reporting all of the lines of the objects which intersect the cut plane line
  • Produce one construction line from the deepest part of the plan and copy along the cut line axis to go faster
  • Reproduce process for the different floors for which you have a plan
  • Lock the layer of these construction lines

Image RemovedImage Added


2. Drawing vertical lines (

15min

0.5 Hour)

  • Do all plans at once in this fashion
  • Start drawing the lines from floor to ceiling (spatial layer)
  • Add the cut lines
  • Add the surface lines

Image Removed

Drawing horizontal lines (35min)

  • Add horizontal lines of handrails (create a block first)
  • Add doorways and windows (create a block first)
  • Add block furniture

    Image Added


    3. Populating section (0.5 Hour)

    • Create block for handrail unit
    • Add handrail unit block to section
    • Repeat above for doors / windows / furniture / other repeated architectural elements in section
    • Add stairs
    • Add hatches

    Image RemovedImage Added



    4. Updating particular spaces (

    100min)

    2 Hour)

    • Create block for individual floors
    • Repeat block for each repetitive floor
    • Assemble all individual sections together (30minfloor blocks together and adjust for permutations (0.5 Hour)
    • Refine differences between floors, atrium and public spaces (70min1.5 Hour)
      • Create the cut outline of the empty void space
      • Put everything in it as light background
      • Add a thin hatch to differentiate the zone from the others
    Image Removed
      • (optional) add light transparent hatch to differentiate continuous void spaces
      • As the void spaces are not repeated per floor, this area requires the highest level of manual drawing and should be allocated the largest amount of time


    Image Added

    Info
    titleLimitations & Disclaimer

    The time estimates represented in this workflow is estimated based on a specific model / input. Actual time required may vary depending on specific use scenarios.

    Here the building is housing with 22 floors or about 560 beds with 60% of one bedroom, 20% of 2 bedrooms, 20% of 3-4 bedrooms.

    Info
    iconfalse
    titleContents
    Steps
    Time
    1Prepare the linework0.5 Hours
    2Drawing vertical lines0.5 Hours
    3Drawing horizontal linesPopulating section   0.5 Hours
    4Updating particular spaces      2 Hours



    Estimated Total Time: 2.5 - 53.5 Hours