Project Scoping and Planning | |||
---|---|---|---|
Item | Description | Deliverables | Status |
Project Scoping/Approval | Create project documentation and gain committee approval |
| COMPLETE |
Project Administration | Staff project and plan for project execution |
| COMPLETE |
Prelimiinary Information Gathering/Analysis | Create punchlist of data cleanup items for further review |
| COMPLETE |
Phase 1: OCLC Validation & Improvements | |||
Information Gathering/Analysis | Select high impact items from error cleanup punchlist, determine scope of issue, determine remediation path. |
| COMPLETE |
Recommendation to Oversight Committee | Provide phase one recommendation report to oversight committee for approval. |
| COMPLETE |
Phase 1 Cleanup Priorities | |||
Paired field errors | This issue occurs in 31,360 fields in 28,396 bib records on file and results in rejection from OCLC. Remediation strategy is automated cleanup from utility (Backstage Library Works).
|
| IN PROCESS
|
'Sparse' records | This issue occurs in 21,538 records on file and results in rejection from OCLC. LTS analysis to determine remediation method(s); initial remediation by LTS in batch followed by outsourcing to utility. |
| IN PROCESS |
Missing Titles (245) | This issue occurs in 855 records on file and results in rejection from OCLC. These require staff review and correction. Report out to libraries for review and manual clean-up. |
| IN PROCESS |
Update lending byte | This issue is present across the entire database. LTS analysis required to further scope remediation options. 14,322,539 holdings records marked 'unknown policy' and 14,500 holdings have invalid values.
|
| IN PROCESS |
Update reproduction byte | This issue is present across the entire database. LTS analysis required to further scope remediation options. 13,672,368 holdings marked 'unknown policy, and 515,184 have invalid values |
| IN PROCESS |
Update retention byte | This issue is present across the entire database. LTS analysis required to further scope remediation options. 140,442 holdings marked 'unknown policy and 9,045,492 have invalid values |
| IN PROCESS |
Invalid identifiers | This issues occurs 12,000 times within 230,000 bibliographic records rejected by OCLC. LTS analysis required to further scope remediation options to update identifier formats and to determine how many records need additional intervention by utilities. |
| IN PROCESS |
Bib/Holdings format conflicts | This issues is occurs in at least 100,000 records and results in rejection from OCLC, but is also an issue across the entire database. LTS analysis required to further scope remediation options to update fixed field and descriptive data to reflect format |
| IN PROCESS |
Active holdings on deleted bibs | This issues occurs in 16,575 holdings at cataloged status for 16,031 bibs that are deleted, and results in records not not being sent to OCLC. Libraries need to review and determine if bibs should be made active or holdings should be marked as deleted. |
| IN PROCESS |
Phase 2: Tier 2 OCLC Validation & Metadata Improvements | |||
Information Gathering/Analysis | Select remaining high impact items from error cleanup punchlist, determine scope of issue, determine remediation path. | Select and complete analysis of phase two issues. | IN PROCESS |
Recommendation to Oversight Committee | Provide phase one recommendation report to oversight committee for approval. | Report | UP NEXT |
Phase 2 Cleanup Tasks | |||
TBD (coming soon!) |
|
| |
Phase 3: Tier 2 OCLC Validation & Metadata Improvements | |||
Information Gathering/Analysis | Select remaining high impact items from error cleanup punchlist, determine scope of issue, determine remediation path. | Select and complete analysis of phase two issues. | UP NEXT |
Recommendation to Oversight Committee | Provide phase one recommendation report to oversight committee for approval. | Report | UP NEXT |
Phase 3 Cleanup Priorities | |||
TBD (coming soon!) |
|
| |
Phase 4: Prepare for potential Aleph, SFX, Verde to Alma Migration | |||
Information Gathering/Analysis | Select remaining high impact items from error cleanup punchlist, determine scope of issue, determine remediation path. | Select and complete analysis of phase two issues. | UP NEXT |
Recommendation to Oversight Committee | Provide phase one recommendation report to oversight committee for approval. | Report | UP NEXT |
Phase 4 Cleanup Priorities | |||
TBD (coming soon!) |
|
|
View a detailed list of metadata optimization candidates.