I. Problem/Value Statement

Problem Statement

Part of the DRS Futures project consists of optimizing the data pipelines that feed the LTS delivery services and creating deliverable copies of files that are separate from their archival and production masters, using a format that is optimized for delivery rather than for long-time preservation. This should result in a drastic reduction of error rates and resource consumption of media delivery services.

Many deliverable files are currently produced by individual departments with ad-hoc developed or outsourced tools, without a central oversight on the quality of the resulting derivatives. A central service for creating derivatives specifically for delivery using community best practices and standards would drastically improve both the overall published media quality and Harvard staff's content production workflows.

Business Value

Creating delivery copies specifically optimized for delivery would have several advantages:

a. Derivatives can be optimized for delivery, resulting in more consistent, and overall much more efficient delivery;

b. Archival and production master files would have a clearly defined purpose and their quality control would be in the content managers' hands, while the optimization of delivery files would be controlled by LTS.

c. If a better encoding for delivery files were found in the future or requirements for delivery formats change, delivery files could be recreated from their masters, without the need to change the latter.

Moreover, campus-wide adoption of an LTS-managed, centralized file conversion tool to consistently produce high quality deliverables at high speed would remove the need for individual departments to come up with their own bespoke solutions for conversion, and would make it possible to completely automate the derivative generation, further relieving DRS stakeholders from repetitive and error-prone work.

II. Vision and Approach

[ To Do ]



Our vision aligns with the following Harvard Library multi-year goals and objectives (MYGOs):

  • MYGO #8: Focus technical services on effective workflows and metadata that matter the most
    • By offering a centralized service for efficient, high-quality, and scalable processing of highly visible (public) files that can be used across campus we would encourage discontinuing one-off solutions that individual departments have been developing for lack of a better alternative, incurring in additional maintenance costs and inconsistent, often substandard output quality.
  • MYGO #10: Focus on space as a service, considering the most cost-effective approaches to user interests, collections security and preservation, and staff needs in HL and HCL facilities
    • [ To Do ]
  • MYGO #14: Minimize the environmental impact of collections, services, and spaces
    • As described in MYGO #10, the goal of this project is to save computing resources, thus reducing the environmental footprint of our services.

Our vision aligns with the following HUIT objectives and key results (OKRs): 

  • Develop a plan for automation in each service area for critical, frequently used or heavily manual workflows
    • This project seeks to optimize one of the most critical and frequently used workflows in the content production chain.

III. In Scope/Out of Scope

In Scope

  • Developing a plug-in for the Vips image library that uses Kakadu for reading and writing JPEG2000 images.
  • Integrating the plug-in into the currently developed imgconv project.
  • Maintaining the plug-in up to speed with future Vips upgrades
  • Documentation and tests for the developed code

Note that this project is limited to still images. Other media may need a different workflow and approach.

Out of Scope

The following items are out of scope because they are achievable without this project; however, an optimized HTJ2K converter would significantly improve their quality:

  • Development of a microservice for converting images based on configurable profiles (imgconv)
  • Integration of imgconv into an automation framework for large scale processing (drs-pipelines)
  • Conversion of defective and/or substandard delivery images into delivery-optmized HTJ2K

IV. Deliverables and Work Products

  • Code, documentation and tests for a Kakadu plugin for Vips in a Git repository.

Definition of Done

This project will be considered done once:

  • The Vips Kakadu plugin code is completed and committed to a Harvard-owned Git repository
  • We are consistently able to compile and run the plugin
  • Comprehensive tests are written for the key functions
  • All tests pass
  • Exhaustive relevant documentation is provided
  • We are able to integrate the delivered code into our imgconv project and verify that the features and options satisfy our needs.

V. Stakeholders

StakeholderTitleParticipation
Stu SnydmanAssociate University Librarian and Managing Director, Library TechnologyExecutive Sponsor, Business Owner















VI. Project Team

Project RoleTeam member(s)
Technical Product Owner / LTSLT OwnerStefano Cossu (LTS)

Software engineers

John Cupitt (independent contractor - development), Pierre-Anthony Lemieux (independent contractor - consulting)*, Brian Hoffman (LTS - integration), JJ Chen (LTS - integration)

QA

Stefano Cossu, Brian Hoffman

Functional documentation

John Cupitt

Scrum Master

Stefano Cossu

Project Manager

Vitaly Zakuta (LTS)

* Pierre-Anthony Lemieux deferred to John Cupitt for carrying out the development, remaining available for advising on Kakadu-specific topics. We have not yet established whether such consulting will be pro bono or for a fee. In the latter case, we should request a cost estimate, but ideally we would like to have one contractor billing for the whole project.

VII. Estimated Schedule (tentative)

PhasePhase StartPhase EndCompletion Milestone

Development & Release

11/27/202312/04/2023

Develop code

Development & Release

12/05/202312/08/2023

Unit and integration tests

Development & Release

12/11/202312/15/2023

Complete & validate documentation

Development & Release

12/11/202312/22/2023

imgconv integration and release

VIII. Assumptions, Constraints, Dependencies, and Risks

Project Assumptions

    • The code delivered by the contractor will be agnostic to external integrations.
    • Integration with imgconv and DRS pipelines, including deployment infrastructure and long-term maintenence, will be the DRS Futures engineering team.
    • Stakeholders will be available to participate in project activities and to complete tasks as requested.
    • The Executive Sponsor and other stakeholders are empowered to make the decisions required for the project to be a success.

Project Constraints

    • Contractor availability
    • DRS Futures team availability
    • Scope
    • Time
    • Budget

Project Dependencies

    • The plugin developer will be need a Kakadu SDK license to perform development, testing, and long-term maintenance of the requested software. Kakadu Software has agreed to provide John Cupitt a free and renewable Kakadu SDK license. The handing-off of that license is underway.

Project Risks

DescriptionPlanImpactOwner
















IX. Acceptance

Accepted by  [ TODO  ]

Prepared by Stefano Cossu

Effective Date: [ TODO ]