Gutman renovation: Spring 2022
Scope of Work Notes Iron Mountain.pdf
First and Second Floor Renovation, 2022-23 (Gutman project notes)
Summary
Gutman will use Iron Mountain to temporarily store items during a planned Spring 2022 renovation (target date to remove items: May 15, 2022).
Timeline
Finalize GEN Inventory project: February 2022
- Collections analysis: February - April 2022
- Packing period and shift of materials off-site: March - May 15, 2022
- Movement of library staff into Phase 1 temporary work spaces: May 15, 2022 - May 30, 2022
- Locations requestable again: TBD May 23rd
- Renovation Construction Phase 1: May 31, 2022 - Jan 31, 2023
- Movement of library staff into Phase 2 work spaces: TBD
- Renovation Construction Phase 2: TBD
Tasklist
Date Completed | Record Type | Task | System | Who | Notes |
---|---|---|---|---|---|
4/18/22 | Alma Configuration- turn off locations | Turn off locations for requesting | Alma | JP, KY | JP send collection codes to be turned off for requests, as well as text for location closure note (Currently unavailable due to construction) Collections turned off (were formerly in circ ffu): GEN, MFIC, MFICP, MFLM, MFLMP, NBS, SQP, THESI, TLL Add note to all non-offsite storage locs |
4/15/22 | Resource sharing | RAPID: Submit a case to RAPID and request they turn off lending for that specific library | RAPID | JP/Jason Clarke | /wiki/spaces/HLILLRS/pages/42698657 |
4/15/22 | Resource Sharing | BorrowDirect: Email James Robinson (jr4511@princeton.edu) and request to turn off that library for lending (and / or as a pickup location) | Borrow Direct | JP/Jason Clarke | /wiki/spaces/HLILLRS/pages/42698657 |
4/15/22 | Resource Sharing |
| ILL | JP/Jason Clarke | /wiki/spaces/HLILLRS/pages/42698657 |
Alma Items | Withdrawing items | Alma | GUT HL staff | HL will generate picklists for IM. They will pull items and create a file of barcodes for items for withdrawal. GUT staff would create sets in Alma, this will verify what was pulled. Julie would then run the withdrawal job. | |
Alma items - ReCAP accessions | Sending items to ReCAP for accession; accessioned as Private (no coding in Alma required) | Alma | HL GUT staff LTS confirmation of method ITS to run batch updates? | GUT will generate picklists for IM. They will pull items and create a file of barcodes for items for accession at ReCAP. GUT staff would create sets in Alma, this will verify what was pulled.
| |
Alma items - HD accessions | Sending items to HD for accession | Alma | HL GUT staff LTS confirmation of method ITS to run batch updates? | GUT will generate picklists for IM. They will pull items and create a file of barcodes for items for accession to HD. GUT staff would create sets in Alma, this will verify what was pulled.
| |
Alma items - Host container/boxed material. Damaged items in stacks | Collections Care processing | Alma | HL GUT staff LTS advising | Destination not yet known – could be placed in storage at Iron Mountain or at HD (depending on scale) LTS suggests using existing preservation work order if possible, TBD |